The three new air compressors of Units 11 and 12 of the third phase of Fengman Power Plant were installed in place, and the installation and commissioning of the air compressor pipeline connection and control system began. The original air compressors used in Units 11 and 12 of Fengman Power Plant have problems such as unstable operation and control system, which poses a major hidden danger to the safe production of the unit. This year, the factory decided to change the original air compressor to one master and two backups. The maintenance department of the plant will undertake the work of replacing the new air compressor. Because it needs to dismantle two old air compressors, and the new air compressor ratio Originally added one, the base of the base and the pipeline and control system need to be re-arranged, and the task is very heavy. The staff of the maintenance department overcame the difficulties of the spring inspectors, the narrow air compressor room, the inconvenience of dismantling and transportation, and strictly implemented the requirements of safe production. Finally, the old air compressor was removed and the new air compressor was installed in place. At the same time, the transformation of the air compressor pipeline and control system is also intensified. According to the requirements of the construction period, the replacement work was completed before May 20, and the new air compressor was officially put into use. Fengman Power Plant in German Military Warehouse Roll Trolleys,Roll Lifting Trolley,Wheels And Handle,Trolley Basket On Wheels Suzhou Malltek Supply China Co.,Ltd. , https://www.oktrolley.com